# Change Request Process: 7 Steps From Request to Decision

> A change request process in seven steps: log, screen, assess, decide, record, update the plan and monitor. Built for firms that agree changes by email and chat.

Louvain, 2026-11-23. Source: https://louvain.ai/blog/change-request-process

# Change Request Process: 7 Steps From Request to Decision

![Abstract isometric change-control process](https://media.babylovegrowth.ai/blog-images/organization-67554/1795298442262_Abstract-isometric-change-control-process.jpeg)

A change request process has seven steps: log the request, screen it, assess its impact, recommend a decision, record the decision, update the plan and monitor the result. Nothing gets worked on until the decision is written down. Most firms already know this. They fail at step one, because the request arrives in an email thread, a meeting aside or a Slack message, and nobody logs it.

This guide gives the full process, where each step goes wrong, and how to keep the record intact when the facts are scattered across inboxes and chats. That is the problem Louvain is built for: it connects your email, documents, meetings, chats and calendar and turns them into checked facts, each cited to its source.

## TL;DR

- A change request is a formal request to alter something already agreed: scope, cost, time or quality.
- The core steps are log, screen, assess, recommend, decide, update the plan and monitor. [APM](https://www.apm.org.uk/resources/what-is-project-management/what-is-change-control/) lists the same sequence.
- No work starts before the decision is recorded. Rejected and deferred requests stay in the log with the reason.
- The usual failure is a request agreed informally in email or on a call and never logged.
- Louvain pulls those informal requests and commitments out of your email, meetings and chats, with a cited source for each.

## Table of Contents

- [What a change request is](#what-a-change-request-is)
- [The seven steps](#the-seven-steps)
- [How to assess impact](#how-to-assess-impact)
- [Who decides, and how to record it](#who-decides-and-how-to-record-it)
- [Urgent, rejected and approved changes](#urgent-rejected-and-approved-changes)
- [Tracking the log](#tracking-the-log)
- [Where the process breaks in real firms](#where-the-process-breaks-in-real-firms)
- [Where Louvain fits](#where-louvain-fits)
- [A one-page change request form](#a-one-page-change-request-form)
- [FAQ](#faq)
- [Sources](#sources)

## What a change request is

The Association for Project Management (APM), the UK's chartered body for the profession, defines a change request in its glossary as [a request to obtain formal approval for changes to the approved baseline](https://www.apm.org.uk/media/wazdsoab/apm-glossary-of-project-management-terms.pdf). The baseline is what everyone signed up to: the scope, budget, timetable and quality standard. A change is anything that moves one of those.

Two examples make it concrete:

- A client on a fixed-fee consulting project asks for a second workshop that was not in the proposal.
- A property manager's contractor asks to move a completion date because a part is delayed.

Both change what was agreed. Both need a decision from someone with the authority to make it.

One distinction saves confusion. APM says change control is a part of the wider discipline of change management, which is about moving an organisation from one state to another. [The two should not be mixed up](https://www.apm.org.uk/resources/what-is-project-management/what-is-change-control/). This article covers the first: controlling changes to an agreed piece of work.

## The seven steps

APM's change control page sets out the sequence: [log the request, evaluate it, assess impact, recommend approval, rejection or deferral, update the plan, then implement and monitor](https://www.apm.org.uk/resources/what-is-project-management/what-is-change-control/). Here it is in practical form, with the point where each step usually breaks.

![Seven steps from request to monitoring](https://media.babylovegrowth.ai/blog-images/organization-67554/1795298569375_Seven-steps-from-request-to-monitoring.jpeg)

### 1. Log the request

Every request gets an entry in one register, whoever raised it and however it arrived. Record an ID, a title, who asked, the date, what they want changed and why.

Where it goes wrong: the request never reaches the register. A client says "could you also cover the Leeds office?" at the end of a call. Someone replies "sure, should be fine" the next morning. That is a scope change agreed in two sentences, and no log has it.

The fix is a rule: anything that alters what was agreed is logged, wherever it was said. The harder part is finding those moments. This is where a tool that reads across email, meetings and chats earns its place, covered below.

### 2. Screen it

A quick first review decides whether the request deserves a full assessment. [Praxis, a project management framework, describes a high-level review](https://www.praxisframework.org/en/knowledge/change-control) that determines whether detailed work is worthwhile. Some requests fail at once: they are out of scope for the contract, duplicate an earlier request, or are too small to justify the paperwork.

Where it goes wrong: screening becomes a veto by whoever is nearest. Give screening to one named person and record the outcome, even when the answer is no.

### 3. Assess the impact

This is the step that costs time, and the one that protects margin. The next section covers it in detail.

### 4. Recommend a decision

The person who assessed the change writes a recommendation: approve, reject or defer. APM's glossary describes change control as the process through which requests are [captured, evaluated and then approved, rejected or deferred](https://www.apm.org.uk/resources/glossary/). Deferral matters more than it sounds. "Good idea, after go-live" is a legitimate answer and keeps the client relationship intact.

### 5. Decide and record

The right person decides, and the decision is written down with the reason. See the section on decision rights below.

### 6. Update the plan

If the change is approved, the baseline changes. Update the scope, fee, schedule, risk list and any deliverable descriptions. Where it goes wrong: the decision is made but the plan is not touched, so the team keeps working to the old version and the new work is unbilled.

### 7. Implement and monitor

Someone owns the work and reports on it. Check that the change delivered what the request said it would, and that its cost and time match the assessment.

## How to assess impact

A good assessment lets the decision-maker say yes or no without a follow-up meeting. The APM Body of Knowledge, 8th edition, says the project manager should first [gauge the effort by size and scale, complexity and feasibility](https://www.apm.org.uk/media/yrwffz0d/apm_bok-8e_sample.pdf). Then assess the effect on:

- scope, objectives and success criteria
- benefits
- time
- cost
- resources
- quality
- risks

The same source advises gathering information from subject-matter experts and from internal and external data, and stating working assumptions about how the change would be implemented.

For a small firm, that comes down to five questions you can answer on one page:

1. What exactly would we do that we are not doing now?
2. How many hours, and whose?
3. What does it cost, and who pays?
4. What does it push back or displace?
5. What could go wrong?

Praxis offers a useful test for the answer. A change should be accepted only if it is [beneficial, practical and affordable](https://www.praxisframework.org/en/knowledge/change-control). Beneficial means it helps the business case or reduces risk. Practical means it works alongside the rest of the specification and other changes. Affordable means the money exists, for example in a change budget or reserve.

### A worked example

This is an illustration, not a real engagement. A consultancy has a fixed-fee project of £60,000 over 12 weeks. The client asks for an extra workshop with its regional managers.

- **Effort:** two days of preparation, one day on site, one day of write-up.
- **People:** a senior consultant and an analyst, both already at capacity in weeks 7 to 9.
- **Cost:** four days at the firm's day rates, added to the fee as a variation.
- **Schedule effect:** the interim report slips by one week unless the analyst is backfilled.
- **Risk:** the regional managers' views may reopen decisions already agreed.

The managing partner reads this and decides: approve with the fee variation and a one-week slip, approve with backfill, or defer to phase two. That is a decision made in five minutes, with the facts in front of her.

## Who decides, and how to record it

Decision rights should be set before the first request arrives. APM's glossary describes a change control board as [a formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines](https://www.apm.org.uk/resources/glossary/). A small firm rarely needs a board. It needs thresholds.

Praxis notes that [thresholds determine whether the decision is made by the project manager, the sponsor or other managers](https://www.praxisframework.org/en/knowledge/change-control). A simple version for a firm of 10 to 50 people:

| Change effect | Decided by |
|---|---|
| No cost, no schedule effect, within scope | Project lead |
| Cost or time effect under an agreed limit | Partner or director on the engagement |
| Above that limit, or any change to contract terms | Managing partner, with the client's written agreement |

Set the limits in pounds and days, not adjectives.

### What the decision record contains

One widely used implementation template sets a clear rule: [no work starts on a change before its decision is recorded, and rejected or withdrawn requests stay in the log with the reason](https://www.ifs-erp.com/en/marketplace/implementation-docs-kit/07-change-request-and-change-control-procedure). Its decision record captures:

- the decision: approved, approved with conditions, rejected, deferred or withdrawn
- any conditions, each with an owner and a date
- the reason, written for someone who reads the log a year later
- who decided, and when
- who was told

The "someone reading in a year" test is worth copying. A reason such as "client declined" is useless. "Client declined the £4,800 variation because the regional rollout moved to Q3" can be used in the next negotiation.

## Urgent, rejected and approved changes

**Urgent changes.** A client escalates on a Friday and wants a yes by Monday. The temptation is to skip the process. Praxis warns that [urgent changes can be pushed through without due process](https://www.praxisframework.org/en/knowledge/change-control). Keep the process and shorten it: one person assesses in an hour, the named decision-maker approves by email, and the log is completed straight after. A short process still leaves a record.

**Rejected requests.** Tell the requester the same day, with the reason. Keep the entry. Rejected requests often return, and the log shows what was already considered.

**Approved requests.** Confirm the new scope, fee and dates in writing to the client and the team. Then update the plan. Praxis adds that recording lessons from each assessment can [speed up future assessments with similar content](https://www.praxisframework.org/en/knowledge/change-control).

If your requests arrive by email, the habit of replying with a clear status matters. This guide to [handling change requests by email](https://voxdonna.com/blog/en/po-change-cancellation-requests-email.html) shows how to apply, review or refuse a request in writing.

Scope creep is what happens when this process is skipped. Our guide on [preventing scope creep before it costs you money](https://louvain.ai/blog/prevent-scope-creep) covers the commercial side.

![Urgent, rejected and approved changes](https://media.babylovegrowth.ai/blog-images/organization-67554/1795298637181_Urgent-rejected-and-approved-changes.jpeg)

## Tracking the log

A log is only useful if people read it. The same template tracks, for each request, the ID, title, who raised it, type, step reached, status, decision date, cost effect, schedule effect, baseline version after the change and owner of the implementation. It also summarises counts of open, approved, rejected or withdrawn and deferred requests, [with cumulative cost and schedule effects for the steering group](https://www.ifs-erp.com/en/marketplace/implementation-docs-kit/07-change-request-and-change-control-procedure).

You can run a smaller version in a shared spreadsheet:

| Field | Why it matters |
|---|---|
| ID and title | One reference everyone uses |
| Raised by, date | Shows where pressure comes from |
| Status | Pending, approved, rejected or deferred |
| Cost and time effect | Totals show the real drift from the original deal |
| Decision, decider, date | Defends the decision later |
| Owner | Someone is accountable for delivery |

The same template makes open change requests a standing item in the weekly team meeting. For a small firm, a five-minute review at the start of the weekly catch-up does the job.

## Where the process breaks in real firms

The steps above are simple. The record is hard, for three reasons.

1. **Requests are made informally.** They sit in email, on calls and in chats.
2. **Commitments are made by people who do not hold the log.** A junior says yes to be helpful.
3. **The evidence is spread out.** When a client disputes what was agreed, someone spends an afternoon searching inboxes and meeting notes.

Confidentiality adds a fourth. A law firm or accountancy cannot paste client emails into any tool that shows them to the wrong people. Whatever helps you find the facts must respect who is allowed to see them.

## Where Louvain fits

Louvain is permissioned company memory for growing teams. It connects your email, documents, meetings, chats and calendar and turns them into checked facts, each cited to its source. You can ask what a client asked for, what was agreed and who agreed it, and the answer traces back to the original message or meeting.

That covers the weak points above. Louvain also tracks commitments, so an informal "yes" made in a thread shows up as something owed. Teams get a daily brief and can see where every project stands, without a status meeting or chasing people in Slack.

Permissions are enforced on every individual fact. Each person, and each AI agent, sees only what they are allowed to see. For firms handling confidential client data, [the security and data handling page](https://louvain.ai/security) explains how.

![Louvain](https://media.babylovegrowth.ai/blog-images/organization-67554/1794490655900_louvain.jpg)

Louvain's Team plan is £20 per person per month and Business is £40 per person per month; Enterprise is priced on request. [See the plans](https://louvain.ai/pricing). Firms in the same line of work can read how it applies to [professional services](https://louvain.ai/solutions/professional-services) or [accounting](https://louvain.ai/solutions/accounting). If you are rolling out Claude or ChatGPT, Louvain works inside them as a connector, giving them permission-aware access to company knowledge.

## A one-page change request form

Use this as a starting template. The University of Leeds' project guide describes a change form as a way to [summarise a specific change and send it to the people who must provide information or approve it](https://deliveringresults.leeds.ac.uk/delivering-results-themes/planning-2/change-control/). Keep yours to one page:

1. **Reference and title.**
2. **Requested by and date.**
3. **What is the change?** Two sentences.
4. **Why is it wanted?** The client's reason, in their words if possible.
5. **Impact:** scope, cost, time, resources, quality, risk.
6. **Recommendation:** approve, reject or defer, with reason.
7. **Decision:** who, when, conditions.
8. **Plan updates made:** fee, schedule, deliverables, who was told.

Train the team on one rule: if the client asks for it and it is not in the agreed scope, it goes on this form before anyone says yes.

## FAQ

### What is the difference between a change request and a change order?

A change request is the proposal to alter what was agreed. A change order, or variation, is usually the signed document that records an approved change and its effect on price and time. The request comes first, and only approved ones become orders.

### How long should the process take?

Set the target by size. Small requests within an agreed limit can be decided the same day by the project lead. Larger ones need a proper assessment, so agree a turnaround, such as three working days, in your thresholds. Urgent requests follow a shortened route with the same record.

### Do small firms need a change control board?

Usually not. A named decision-maker for each threshold is enough, as in the table above. APM describes a change control board as a formal group of stakeholders, which makes sense on large programmes. For a firm of a few dozen people, one partner with clear limits works.

### What should I do when a client says yes on a call and nobody logs it?

Log it as soon as you spot it, assess it as normal and confirm the outcome to the client in writing. Then find out how it was missed and add a rule. Louvain turns meeting and email content into cited facts and tracks commitments, which helps you find these moments.

## Sources

- [APM Glossary of Project Management Terms](https://www.apm.org.uk/media/wazdsoab/apm-glossary-of-project-management-terms.pdf)
- [APM: What is change control?](https://www.apm.org.uk/resources/what-is-project-management/what-is-change-control/)
- [APM: Project management glossary](https://www.apm.org.uk/resources/glossary/)
- [APM Body of Knowledge 8th edition sample](https://www.apm.org.uk/media/yrwffz0d/apm_bok-8e_sample.pdf)
- [Praxis Framework: Change control](https://www.praxisframework.org/en/knowledge/change-control)
- [Change request and change control procedure template](https://www.ifs-erp.com/en/marketplace/implementation-docs-kit/07-change-request-and-change-control-procedure)